CNO - HVRT&LVRT Technical document V1 de 2024
CNO - Consejo Nacional de Operación
Descargar PDF
Disponible
Detalles
- Título
- CNO - HVRT&LVRT Technical document V1 de 2024
- Autor
- CNO - Consejo Nacional de Operación
- Categoría
- Infralegal
- Área del derecho
- Servicios Públicos
- Año
- 2024
SG3125HV-30 Series
LVRT &HVRT FUNCTION
Technical InformationConfidential SG3125HV-30 LVRT & HVRT FUNCTION The grid faults require the support from PV inverters by staying connected to the grid and generating reactive currents to support the grid voltage in corresponding grid code. These currents are related to the correct dimensions of the wiring and protection devices at the PV plant and grid levels. Therefore, maximum values of short-circuit currents or characteristic values (as for example Ik’’ and Ip) and currents at defined times during voltage drop need to be confirmed.
SG3125HV-30 Series Short Circuit Current SG3125HV-30 will stay connected from the grid in the event of voltage drop and support the grid voltage by feeding a reactive current into the grid according to a certain characteristic. These apply to all types of short circuits (i.e. to single-phase, two-phase and three-phase short circuits).
The voltage drop causes an immediate reaction of the PV inverter with the peak short-circuit current Ip which is just a peak of max. 40 μs with no significant area under the current characteristic curve; afterwards, the inverter limits the current immediately to prevent the inverter from thermal overload, with the initial symmetrical short-circuit current Ik'' which will not last longer than 30ms.
The value for the steady -state short-circuit current Ik will be reached after 30 ms and will be maintained during the entire duration of the voltage drop. Furthermore, the value of feed-in reactive current are related to the remaining voltage and the k-factor (default k-factor = 2).
Figure 1. Principle of voltage support in the event of grid fault
The response of voltage drop contains one static and two dynamic parts, as shown in the Figure 1. The instantaneous values of AC currents and voltages are recorded synchronously with 50 kHz (20 μs). Positive sequence component is based on measurement of instantaneous voltages and currents are calculated according to IEC 6140021 (2008). The following table shows the test results for SG3125HV-30.Confidential
μs). Positive sequence component is based on measurement of instantaneous voltages and currents are calculated according to IEC 6140021 (2008). The following table shows the test results for SG3125HV-30.Confidential
Low Voltage Righ Through (LVRT) Technical Requirements for Connecting Photovoltaic Power Station to Power System requires medium-and-large PV plant should be equipped with Low Voltage Ride Through (LVRT) ability.
LVRT requires: PV plant can operate normally within certain voltage drop range and duration when the voltage of the grid -connected point drops due to the power system failure or disturbance; PV plant can provide the dynamic reactive power support during the period.
Dynamic Reactive Current Support During LVRT, power station should feed reactive current to the power system as per requirements. For a station whose 500kV or 750kV voltage is stepped up from the 220kV or 330kV voltage and then connects to the power station group, it should feed reactive current to the grid when a shortcircuit occurs and the voltage drops.
Zero Voltage Ride Through When the grid-connection point voltage drops to zero, the power station can operate normally for 1 second. UT is the grid-connection point voltage; Upu is the grid-connection point nominal voltage.
Figure 2 Low voltage withstand requirements Note: T1, T2, U1, and U2 are all settable parameters. For the specific range and default value, refer to Protection parameter range and default value
The LVRT parameters can be set to meet the different requirements of different grid codes
Parameters Range Setting Descriptions LVRT switch Enable/Disable Enable Enable or disable the HVRT switch LVRT T1(ms) 40~36000000 20000 Setting for starting time for LVRT stage 1 LVRT T2(ms) 40~36000000 1500 Setting for starting time for LVRT stage 2Confidential LVRT T3(ms) 40~36000000 500 Setting for starting time for LVRT stage 3
LVRT T4(ms)
LVRT T2(ms) 40~36000000 1500 Setting for starting time for LVRT stage 2Confidential LVRT T3(ms) 40~36000000 500 Setting for starting time for LVRT stage 3 LVRT T4(ms) 40~36000000 500 Setting for starting time for LVRT stage 4 LVRT T5(ms) 40~36000000 500 Setting for starting time for LVRT stage 5 LVRT voltage1(%) 0~90 90 Setting for starting L VRT stage 1. The setting should meet the local grid standard. LVRT voltage2(%) 0~90 85 Setting for starting LVRT stage 2. The setting should meet the local grid standard. LVRT voltage3(%) 0~90 10 Setting for starting LVRT stage 3. The setting should meet the local grid standard. LVRT voltage4(%) 0~90 10 Setting for starting LVRT stage 4. The setting should meet the local grid standard. LVRT voltage5(%) 0~90 10 Setting for starting LVRT stage 5. The setting should meet the local grid standard. LVRT dynamic Var Kf factor 0~10 2 Ratio of reactive power compensation and voltage dip depth during LVRT
High Voltage Ride Through (HVRT) Technical Requirements for Connecting Photovoltaic Power Station to Power System requires that the PV plant can operate as required within certain voltage range.
Grid-connection point voltage Requirements 1.1Upu<UT<1.2Upu Operate for at least 10s 1.2Upu≤UT≤1.3Upu Operate for at least 0.5s Note: UT is the grid-connection point voltage; Upu is the grid-connection point nominal voltage.
Figure 3 High voltage withstand requirementsConfidential Parameters Range Setting Descriptions HVRT switch Enable/Disable Enable Enable or disable the HVRT switch
Note: UT is the grid-connection point voltage; Upu is the grid-connection point nominal voltage.
Figure 3 High voltage withstand requirementsConfidential Parameters Range Setting Descriptions HVRT switch Enable/Disable Enable Enable or disable the HVRT switch HVRT T1(ms) 40~36000000 2000 Setting for starting time for HVRT stage 1 HVRT T2(ms) 40~36000000 2000 Setting for starting time for HVRT stage 2 HVRT T3(ms) 40~36000000 2000 Setting for starting time for HVRT stage 3 HVRT T4(ms) 40~36000000 2000 Setting for starting time for HVRT stage 4 HVRT T5(ms) 40~36000000 2000 Setting for starting time for HVRT stage 5 HVRT voltage1(%) 110~140 110 Setting for starting HVRT stage 1. The setting should meet the local grid standard. HVRT voltage2(%) 110~140 110 Setting for starting HVRT stage 2. The setting should meet the local grid standard. HVRT voltage3(%) 110~140 110 Setting for starting HVRT stage 3. The setting should meet the local grid standard. HVRT voltage4(%) 110~140 110 Setting for starting HVRT stage 4. The setting should meet the local grid standard. HVRT voltage5(%) 110~140 110 Setting for starting HVRT stage 5. The setting should meet the local grid standard. HVRT dynamic Var Kf factor 0~10 2 Ratio of reactive power compensation and voltage dip depth during HVRT
Dead band settings
The reactive current activation threshold is determined by the setting configured for the voltage dead band. Below are the voltage dead band settings:
LVRT HVRT Range Setting Range Setting 0 - 100% 90% 100-140% 110%
Dead band settings
The reactive current activation threshold is determined by the setting configured for the voltage dead band. Below are the voltage dead band settings:
LVRT HVRT Range Setting Range Setting 0 - 100% 90% 100-140% 110% 0 - 600 V 540 V 600 - 840 V 660 V
Reactive current injection is determined by the LVRT Dynamic Var Kf factor and HVRT Dynamic Var Kf factor. See LVRT and HVRT settings for details.